GOES-14 Science Test December 2009

Don Hillger, Deb Molenar, Dan Lindsey, John Knaff

NOAA/NESDIS/STAR/RAMMB

Dave Watson, Mike Hiatt, Dale Reinke, etc.

CIRA, Colorado State University

Fort Collins CO

Previous GOES Science Tests



GOES-13 Science Test – December 2006: NOAA/NESDIS TR 125 and BAMS article



GOES-14 Science Test report: NOAA Technical Report NESIDS 131 PDF available online, or on compact disc



GOES Science Test Goals

For all GOES check-outs, the goals of the Science Test include the following:
  • To assess the quality of the GOES radiance data. This is accomplished by comparison to other satellite measurements or by calculating the signal-to-noise ratio compared to specifications, as well as assess the striping in the imagery due to multiple detectors.

  • To generate products from the GOES data stream and compare to those produced from other satellites. These included several Imager and Sounder products currently used in operations.

  • To collect rapid-scan and other special imagery of interesting weather cases, with temporal resolutions as fine as every 30 seconds for severe weather, a capability of rapid-scan imagery from GOES-R that is not implemented operationally on current GOES.

  • To help resolved any issues relating to the GOES data delivered to users.



GOES-O baseline plan – 2009 June

Launch – 6/26/09

• LAM burn 1 – 6/28/09

• LAM burn 2 – 7/1/09

• LAM burn 3 – 7/3/09

• LAM burn 4 – 7/5/09

• LAM burn 5 – 7/7/09

• Solar array deployment – 7/8/09

• Magnetometer boom deployment – 7/12/09

• PLT Start – 7/16/09

• Engineering Handover – 7/17/09

• SXI 6.29 Load – 7/20/09

• XRP Deploy – 7/23/09

• XRS/EUV Power-on – 7/23/09

First Public Imager Full Disk Images – 7/27/09

• First Public SXI Image – 8/5/09

• Drift Control maneuver – 8/6/09

• Imager/Sounder Cooler Cover Deployment – 8/14/09

First Public IR Image – 8/16/09

• INR Start-up – 8/27/09 to 9/3/09

• Contingency Operations Readiness Review (CORR) – 9/10/09

• IMC Spec Testing – 9/13/09 to 10/29/09

• NSSK 1 Maneuver – 10/30/09

• EWSC to 105W Maneuver – 11/9/09 to 11/21/09

• NSSK 2 Maneuver – 11/27/09

NOAA Science Testing – 11/30/09 to 12/14/09

• Operations Acceptance Review (OAR) – 12/14/09

• PLT End – 12/14/09

GOES-14 NOAA/Science Test Website



GOES-15 RAMSDIS Online



GOES-15 CIMSS Satellite Blog



GOES-15 publicity from NESDIS/STAR



First GOES-14 Visible Image 1730 UTC 27 July 2009



First GOES-14 IR Images 1730 UTC 17 August 2009



First GOES-14 Solar X-ray Image 1400 UTC 13 August 2009



GOES-14 Science Test December 2009

  • Five (5) weeks:

    • Starting: 30 November 2009
    • Ending: 04 January 2010
  • Eight (8) pre-determined schedules (See http://rammb.cira.colostate.edu/projects/goes-o/#schedules

  • Daily schedule changes (at 1630 UTC), determined by test coordinators, based on feedback from participating scientists

  • GOES-14 was located at 105°W during the Science Test

  • Afterwards, GOES-14 was kept in normal mode and the solar instruments only were operational.



GOES-O Test Schedules



Limb Sounding (for noise/striping)



CONUS Imager (product generation)



CONUS Sounding (product generation)



Imager rapid-scan (lightning/radar)



Overlapping (ABI 2 km emulation)



GOES-14 Coordination/Timing



Participating Sites



GOES-14 Science Test Preliminary Results

  • First official GOES-14 images were collected from Imager (visible and IR) and Sounder

  • Improved (4 km) resolution of 13.3 µm band required changes to GVAR format.

  • Several issues with implementing the new GVAR format were discovered and are being rectified, both at the front end, and at GVAR receiving sites.

    • Paired detectors on the higher-resolution 13.3 µm band were inadvertently swapped. Now fixed.
    • Image navigation issues have been addressed (McIDAS server software was upgraded.)


Results of Science Test: Noise levels for all GOES



GOES-14 Science Test

  • Questions? (Don.Hillger@NOAA.gov)

  • One stop for GOES-14 Science Test:

http://rammb.cira.colostate.edu/projects/goes-o/

  • Tim Schmit (more Science Test results) presentation to follow!



Схожі:

Goes-14 Science Test December 2009 iconGoes-14 Science Test December 2009

Goes-14 Science Test December 2009 iconDewitt physical therapy December, 2009 outline prevalence and Cost

Goes-14 Science Test December 2009 iconSeasonal and Diurnal Variations of Atmospheric Mercury in Houston, Texas Xin Lan, Patrick Laine, Barry Lefer, and Robert Talbot Institute for Climate and Atmospheric Science, Department of Earth and Atmospheric Science University of Houston, Houston, tx 77204.

Goes-14 Science Test December 2009 iconDecember 13, 2012 Members Generosa Grana*

Goes-14 Science Test December 2009 iconChandra Science Highlight

Goes-14 Science Test December 2009 iconAn innovative training course in Political Science

Goes-14 Science Test December 2009 iconForefront of neutron star science Forefront of neutron star science

Goes-14 Science Test December 2009 iconFreezing rain event 14-15 December 2005 Central South Carolina Introduction

Goes-14 Science Test December 2009 iconTiming Relativistic Binary Pulsars to test Gravitation and measure ns masses Paulo C. C. Freire

Goes-14 Science Test December 2009 iconAstronomy 340 Fall 2007 4 December 2007 Lecture #26 Extrasolar Planets


Додайте кнопку на своєму сайті:
dok.znaimo.com.ua


База даних захищена авторським правом ©dok.znaimo.com.ua 2013
звернутися до адміністрації
dok.znaimo.com.ua
Головна сторінка